Inspector, Computation Office.
SURVEY OF EGYPT PAPER No. 39.
To be obtained, either directly of through any Bookseller, from the GOVERNMENT PUBLICATIONS OFFICE, Ministry of Finance.
(Dawawin P.O.), Cairo.
Price - - - - - - - P.T. 10.
MINISTRY OF FINANCE,
EGYPT.
____________
Size and Orientation of the Great
Pyramid of Gîza.
In the beginning of April 1925 Prof. Borchardt of the German Institute of Egyptian Archaeology asked the Survey of Egypt for the loan of surveying of the Great Pyramid of Gîza.
After consultation with Mr. R. Engelbach, Chief Inspector Antiquities Department, it was agreed that the Survey of Egypt would carry out the necessary measurements after Prof. Borchardt had done the necessary excavations and clearing to find the original base of the Pyramid on all four sides.
The construction of the Pyramid on the outside was as follows: The desert was cleared down to solid rock and on this rock was built a pavement which was accurately levelled. The actual base of the Pyramid was laid out on this pavement leaving about 40 centimetres width of pavement all round the bottom edge of the casing blocks: This width is, however, not exactly the same on all four sides, it being 38 centimetres on the western side, 42 centimetres on the northern side, and 48 centimetres on the eastern side, at the places where it could be measured. At the four corners of the Pyramid the rock was cut away, giving a greater depth for the foundations of these points. These excavations are rectangular in form and are called the corner sockets. The purpose of these present survey is to determine as accurately as possible the exact size, shape and orientation of the original base of the Pyramid on the pavement.METHOD OF SURVEY.
FRAME WORK.
Eight brass bolts were cemented into the rock round the base, one near each of the fore corners, and, as these were not intervisible, four more were placed, one at about the middle of each side, in such a position that each point was visible from the adjacent points on each side of it.These bolts are numbered from 1 to 9 clockwise from No. 1 which is at the S.E. corner of the Pyramid.
The positions of these points were determined by means of precise traverse observations.
The distances were measured with the Base Line Apparatus designed by M. M. Benoit and Guillaume using 24 metre standardised invar wires. Each length was measured twice with different wires with an accuracy of about 1 in 500,000.
The angles were measured on 4 arcs with a 6 inch Troughton and Simms micrometer theodolite.
The top of the flagstaff on the top of the Pyramid was visible at points1, 6 and 7 and was included in the round of angles at these stations.
The closure in angle of this traverse was found to be 9.6” which was adjusted by adding 1.2” to each angle.
Using these adjusted angles, the co-ordinates were computed and a closing error of 8 millimetres in North direction and 0 millimetre in East direction was found. These co-ordinates were adjusted by the normal traverse method for closure.
The position of the top of the flagstaff was computed from the intersection of the sights at points 6 and 7. The computed horizontal angle at 1 to the top of the flagstaff and point 2 was found to check with the observed angle within 3.0” of arc.
AZIMUTHS.
The azimuth of the line 6 to 7 was obtained by observations taken on Polaris near elongation against time. The final azimuth was the mean of two arcs taken both face left and face right. The time was taken on a Zenith watch rated to keep sidereal time. The error of the watch was determined by vertical circle readings on both faces for both an East and West star against time. The latitude of station 6 was computed from the known geodetic latitude of E1, on the Great Pyramid and the distance of 6 North of E1.
The azimuth of
7 from 6 was found to be:-
119º 11”
07.1” East of true North.
EXCAVATION OF PAVEMENT.
NORTH SIDE.- The whole of the pavement, where it existed on the North Side, was cleared and the original line of the edge of the casing blocks on it was found for a distance of 55 metres. On 20 metres of this, the casing blocks are still in position.
EAST SIDE.- An excavation was sunk down to the pavement, starting from the centre of the side and extending 30 metres to the north. In this excavation the bottom edge of the casing blocks was found, giving a clear line for almost the entire length of the excavation.
SOUTH SIDE.- Five pits were dug at various places along the edge: in four of these it was found that the casing blocks and pavement had been destroyed. In one, the top edge of the casing block was still in place and the excavation was extended as far as possible along this edge, which was found for a distance of 18 metres, the edge being clearly defined for a distance of 15 metres.
WEST SIDE.- Four pits were sunk, the pavement being found in 3 of these.
In the fourth, the pavement had been entirely destroyed. The maximum length of the line given from these three holes was 28 metres.
PRECISE LEVELLING.
Before attempting to survey these lines, it was decided that it would be a useful check as to whether they really were on the pavement or not, if we determined the levels of each point.Paints marks were made at various places on the pavement and casing
blocks, where they were found in the holes, and a line of precise levelling
was rum connecting each point with two Precise Bench Marks already established
at the Pyramid. The descriptions of the points and their reduced levels
above M.S.L. at Alexandria are given in the following list.
B M. |
DESCRIPTION OF POINTS |
VALUE |
North East Corner. |
||
1 |
Bottom of N.E. corner-socket ………………………………... |
59.6958 |
2 |
Rock W. of B.M. 1= foundation of pavement ……………….. |
59.8913 |
North Side. |
||
3 |
Top surface of pavement W. of 2 (beginning of pavement) at B. on diagram ………………………………………………. |
60.4129 |
4 |
Top surface of pavement E. if remaining casing-blocks ……... |
60.4049 |
5 |
Top surface of casing block (near 4) …………………………. |
61.9011 |
6 |
Top surface of pavement W. of remaining casing-blocks at A. |
60.4115 |
7 |
Top surface of casing block (near 6) …………………………. |
61.9077 |
North West Corner. |
||
8 |
Rock E. of N. W. corner socket = foundation of pavement ...... |
59.8584 |
9 |
Bottom of N.W corner socket ………………………………... |
59.6034 |
West Side. |
||
10 |
Rock in hole L= foundation of pavement …………………….. |
59.8841 |
11 |
Top surface of pavement in hole K …………………………... |
60.4129 |
12 |
Top surface of casing block in hole K ………………………... |
61.9148 |
13 |
Top surface of pavement in hole J …………………………... |
60.4154 |
South West Corner. |
||
14 |
Rock N. of S.W. corner socket = foundation of pavement ...… |
59.8798 |
15 |
Bottom of S.W. corner socket ……………………………...… |
59.8485 |
South Side. |
||
16 |
Rock in hole H – top surface of pavement …………………… |
60.4222 |
17 |
Top surface of casing block in hole H ………………………… |
61.9333 |
18 |
Top surface of pavement in hole G ………………………...… |
60.4229 |
19 |
Top surface of pavement in hole F ………………………….… |
60.4264 |
South East Corner. |
||
20 |
Bottom of S.E. corner socket ………………………………… |
59.3700 |
21 |
Rock W. of S.E. corner socket = foundation of pavement …… |
59.8305 |
East Side. |
||
22 |
Top surface of pavement in the southern end of the hole C ….. |
60.4193 |
23 |
Top surface of pavement the northern part of the hole C …….. |
60.4210 |
MEASUREMENT OF THE BASE OF THE PYRAMID.
The method adopted for surveying the actual base of the Pyramid, i.e. the lines of the bottom edge of the casing blocks on the pavement, was as follows :-The 6 inch theodolite was set up on one edge of the excavation as near as possible in the line of the edge of the casing blocks still traceable on the pavement at the bottom of the excavation. It was them adjusted by means of the sliding head on the tripod until the marks on the extreme ends of the line on the pavement fell accurately on the centre hair of the telescope as it was revolved about its horizontal axis, the horizontal plate being level and clamped rigidly. A mark was then placed in the ground at the far end of the line, so that it also fell on the centre hair of the theodolite.
This mark was checked, using the opposite face of the theodolite.
The theodolite was set up over this mark, and after checking to make sure that the vertical hair would accurately traverse the line with the horizontal circle clamped, a second mark was placed on the ground, at the other end, in the continuation of the line. This mark was also checked on both faces.
The line between the two marks was extended in both directions by means of the theodolite, until it intersected the mail traverse lines at each end.
A mark was placed in the ground at each point of intersection.
This method was used on all four sides of the Pyramid, with a slight modification on the South side, since the top edge of the casing had to be taken, as the bottom edge was totally destroyed.
The whole work was repeated two or three times ab initio ; the maximum difference in position of the final marks was bout 3 centimetres, this being on the extension of the short southern edge. The mean position for each mark was taken as the best obtainable position.
The short distances between these marks and the nearest traverse points were measured with a standardised steel band graduated in centimetres and read to millimetres by estimation.
The co-ordinates
of the points of intersection of the sides and the main traverse were found,
and the equations of the four sides were written down. These equations
were solved in pairs to give the co-ordinates of the corners of the Pyramid.
From these co-ordinates the lengths and azimuths of all four sides and the
two diagonals were found.
These are as follows :-
Side. |
Length. |
True Azimuth. |
||
Metres. |
º |
‘ |
“ |
|
North |
230.253 |
89 |
57 |
32 |
South |
230.454 |
89 |
58 |
03 |
East |
230.391 |
359 |
54 |
30 |
West |
230.357 |
359 |
57 |
30 |
N.E. – S.W. |
325.699 |
44 |
56 |
45 |
N.W. – S.E. |
325.868 |
314 |
57 |
03 |
The position of the South side was found from the actual prolongation of the whole of the existing top edge of the casing blocks, to which the bottom edge was assumed exactly parallel, and the horizontal distance of 5.5/7 times the vertical height of the edge above the pavement. This height is given in the list of levels, namely No. 17 to No. 16, and is 1.511 metres. Therefore the distance to be added is 1.511 X 5.5/7 + 1.187 metres to the south of the line of the top of the casing. This distance has been added to get the co-ordinated of the south-east and south-west corners, and hence the actual lengths of the sides. In justification of using this constant of 5.5/7, reference should be made to W.M. Flinders. The Pyramids and Temples of Gîza in which he gives the angle of slope as 51º 50’ 40” ± 1’ 05” also Borchadt, Gegen die Zahlenmystik an der grossen Pyramide ; finally a further check was made by measuring up the slope of the existing casing-stones on the North side. This gave approximately 1.173 metres as the horizontal distance for a difference in height of 1.496 metres (from points 4 to 5). The theoretical distance horizontally of 1.175 millimetres agrees within the limits of accidental error of the actual measurement.
The mean dimensions of the Pyramid are thus : -
Central Axis. |
Length. |
Azimuth. |
||
Metres. |
º |
‘ |
“ |
|
North to South |
230.374 |
359 |
56 |
00 |
East to West |
230.354 |
89 |
57 |
48 |
General Mean |
230.364 |
- |
3 |
06 |
Side |
Length Petrie 1880 |
New Determination 1925. |
Difference. |
Ins. |
Ins. |
Ins. |
|
North ………….. |
9069.4 |
9065.1 |
- 4.3 |
South ………….. |
9069.5 |
9073.0 |
+ 3.5 |
East …………… |
9067.7 |
9070.5 |
+ 2.8 |
West …………... |
9068.2 |
9069.2 |
+ 0.6 |
Mean |
9068.8 |
9069.4 |
+ 0.6 |
From which we obtain the mean differences on the central axis :-
Axis. |
Petrie minus Cole. |
Ins. |
|
North to South ………… |
+ 1.7 |
East to West …………… |
- 0.4 |
Mean dimension ………. |
+ 0.6 |
This very close agreement of these mean dimensions shows the accuracy with which Prof. Flinders Petrie determined the data on which he based his assumptions.
The comparison of azimuths is as follows :-
Side. |
Azimuth Petrie. |
Azimuth Cole. |
Difference |
|||
‘ |
“ |
‘ |
“ |
‘ |
“ |
|
N ………………. |
- 3 |
20 |
-2 |
28 |
+0 |
52 |
E ………………. |
- 3 |
41 |
-1 |
57 |
+1 |
44 |
S ………………. |
- 3 |
57 |
-5 |
30 |
-1 |
33 |
W ……………… |
- 3 |
54 |
-2 |
30 |
+1 |
24 |
- 3 |
43 |
-3 |
06 |
+ |
37 |
to N.E. corner
= 115.161 metres
to N.W. corner = 115.090 metres
Diff. = 71 millimetres.
Thus this line is probably the original line of the axis.
MAXIMUM ERRORS TO
BE EXPECTED IN THE NEW
DETERMINATION.
SOUTH SIDE:- This is the extension of 15 metres of the top edge of the casing blocks. The 15 metres chosen are unworn and give a very definite line to work from. The final extension should be correct to 1 centimetre on the West end and 3 centimetres on the East end, to which must be added any error there may be in the computed horizontal distance between the top and the bottom edges of the casing blocks.
* Petrie op. Cit. P. 39.
WEST SID.- This is the extension of points in the pavement 28 metres apart. The pavement is badly worn in most places, as are also the casing blocks which are still in place. The points chosen are however fairly definite and there is little doubt that they are correct. The final errors at either end should be less than 3 centimetres.It should be clearly understood that these possible errors are due to uncertainty of the absolute position of the line on the pavement since a difference of 1 millimetre only at either end of the line on the excavation will make a difference of 5 millimetres or more at each end of the extended side, to which must be added the possibility of slight deviation of the original side from the straight line. Checking along the 55 metres on the northern edge has shown this is likely to be inappreciable.
The position of the points of intersection of the adjacent sides was also ground on the corner sockets, and measurements were taken from these points to the outside edges of the socket where they existed.
The South Western corner socket was too broken to give any information. For the other three sockets, the following measurements were found :-
Socket. |
Edge. |
Distance. |
|
cms. |
|||
N.E. |
{ |
N E |
85 85 |
S.E. |
{ |
S E |
83 85 |
N.W. |
{ |
N W |
75 76 |
From these measurements we see that the corners of the Pyramid obtained from the extension of the sides actually fall on the diagonals obtained from the socket corners where these can be determined, thus giving additional confirmations that the size and orientation of each side a found above is very close to the truth.