by Duggan Flanakin
July 14, 2026
from
RealClearEnergy Website
Article also
HERE
|
Duggan Flanakin
is a senior policy
analyst at the Committee For A Constructive Tomorrow who
writes on a wide variety of public policy issues. |

Under Trump's EO,
Four
Companies have jumpstarted
America's
Nuclear Race.
Four reactors hit criticality,
beating
the president's July 4 deadline.
On May 23, 2025, President
Trump, via
Executive Order 14301, took
multiple actions to jumpstart the nation's long-dormant nuclear
energy industry.
Besides "expeditiously" processing applications
for qualified test reactors and revising agency policies to further
expedite review, approval, and deployment of advanced reactors under
Energy Department supervision.
The goal was to enable operational test microreactors within two
years following a completed application.
Toward that end, the DOE created a pilot program
with a goal of construction and operation of at least three reactors
outside the National Laboratories (but under a DOE contract) to
achieve "criticality" by July 4, 2026 - the nation's 250th birthday.
Last August the DOE selected
11 reactor projects for the pilot
program and offered them land and support from the national
laboratories system - every effort to fast-track success.
Four of them -
Antares Nuclear Inc.,
Valar Atomics, and
Aalo Atomics (which got there
the morning of July 4), all founded in 2023, made the
President's first deadline.
But so did one-year-old
Deployable Energy, whose test
reactor was the first to reach criticality under the DOE's
Nuclear Energy Launch Pad, a joint project of the Idaho National
Laboratory and the National Reactor Innovation Center in June
2025.
The Launch Pad, which builds on the
success of the Reactor Pilot Program and the Fuel Line
Pilot Program, provides assistance for advanced reactors, fuel
fabrication, enrichment, reprocessing, and related innovations.
Criticality is a technical milestone that establishes a reactor
can sustain a chain reaction - but that alone does not mean the
reactor can provide electricity.
Zero-power criticality
can be achieved
without meaningful engineering progress on fuel or design.
So,
what have these firms achieved - and how
about the progress of the other eight grant recipients?
Antares Nuclear's Mark-0 test reactor
achieved criticality on June 4 at Idaho National Laboratory as the
first privately funded non-light-water design to go critical there
in four decades.
The Mark-0 is a sodium heat-pipe-cooled
design running NALEU TRISO fuel.
Antares had been testing at NASA's Marshall Space Flight
Center with the aim of providing 100 kw of nuclear energy to a
future moon base.
The firm already has an order to deliver its
microreactors to Joint Base San Antonio in 2027.
Valar Atomics' minivan-sized Ward 250,
reached criticality on June 22 at its test site at the San Rafael
Energy Lab in Utah after also reaching criticality in a core-only
test at Los Alamos National Laboratory.
The Ward 250 is a TRISO-fueled, helium-cooled,
high-temperature gas reactor.
Aalo's Critical Test Reactor (CTR) went from groundbreaking
to criticality on July 4, eight months after startup, before an
audience of all 200 company employees for what CEO Matt Loszak
described as "a nuclear Burning Man."
Aalo's success has greenlighted construction of a
10-Mwe reactor that can power an on-site data center to be
deployable by 2027.
Deployable Energy's test reactor is water-moderated and
helium-cooled and runs on standard 4.95% enriched uranium dioxide
with
commercially available materials instead of HALEU or
exotic components.
Founder Bobby Gallagher partnered with
Texas A & M University's nuclear engineering department on a 1-MW
container reactor, the Unity Nuclear Battery.
The DOE says no other country had ever taken three - no, four -
distinct advanced microreactor designs critical in a single 30-day
period.
Energy Secretary Chris Wright called the
joint accomplishments,
"a significant milestone on a timeline many
thought was unachievable."
These firms meeting the July 4 deadline marks a
major milestone for President Trump's initiative to incentivize a
nuclear energy renaissance, according to the DOE.
In just one year, the nation has taken bold steps
to remove excessive regulatory barriers, give new life to retired
nuclear power plants, and secure a domestic nuclear fuel supply
chain.
All of the other initial grant recipients are also making progress
toward criticality and deployment.
Deep Fission is building a 15 MWe modular reactor prototype
that will be placed in an optimized borehole 1 mile beneath the
earth's surface in Parsons, Kansas.
The Gravity Nuclear Reactor design uses
pressurized water reactor technology and low-enriched uranium fuel;
the tiny footprint and dense power output enable multiple units on a
single site.
Just this month the factory-built, non-nuclear prototype canister
was delivered to the Kansas site, a major step toward validating
installation, infrastructure readiness, and operational sequencing
before fuel loading.
Deep Fission, whose project is beginning
real-world installation and testing, anticipates achieving
criticality very soon.
On July 1, Oklo Inc.
announced that the DOE had approved the
Documented Safety Analysis for its Isotopes' Groves Isotope Test
Reactor.
As soon as Oklo passes the DOE's readiness
review and gains approval for startup, the facility will load
nuclear fuel, conduct startup testing, and proceed towards
criticality - which it hopes to achieve by the end of July.
Oklo also signed an Other Transaction
Authority with the DOE to support the design, construction, and
operation of a radioisotope pilot plant under the Reactor Pilot
Program.
Atomic Alchemy Inc., an Oklo subsidiary, will use the
Radioisotope Pilot Facility to lay the groundwork for future
commercial plants that make medical and research radioisotopes.
Radiant Energy's Kaleidos 1 MWe portable microreactor in
February
won DOE approval to proceed toward a full-power test of its
design at Idaho National Laboratory.
Kaleidos, which uses fans and an air jacket to
cool the core through natural convection (and no on-site water), is
built for diverse environments and provides 1.9 MW of thermal power
for facility heating or desalination.
If all goes well, Radiant will build a
larger reactor in Oak Ridge, Tennessee.
Back in February, Terrestrial Energy Inc. executed an
agreement with the DOE for a pilot reactor that will support the
design and safe operation of the TETRA reactor, a
molten-salt-fueled, graphite moderated reactor that will use
standard assay, low-enriched UF4-based fuel (SALEU) containing less
than 5% uranium-235.
Last September, Terrestrial Energy was
also selected for the DOE's Fuel Line Pilot Program.
In May,
the DOE approved the Preliminary Documented Safety Analysis
for Last Energy Inc.'s PWR-5 pressurized water pilot reactor, to be
built at Texas A & M's Rellis Campus.
The action clears the way for fuel receipt,
criticality demonstration and operations. The firm is also engaged
with the NRC in pre-application activities for its planned PWR-20, a
20-MW pressurized water microreactor, to be built in Haskell, Texas.
Natura Resources LLC, is on track to deploy its 1-MW,
high-temperature, low pressure MSR-1 liquid-fuel Gen IV molten salt
reactor later this year at its demonstration site on the campus of
Abilene Christian University.
The NRC issued a construction permit for the
reactor in September 2024, and Natura is now preparing for an
operating license application.
The project intends to advance Gen IV molten
salt reactor technology with dual applications in energy and
medicine.
Dozens of other nuclear energy startups - and
older companies - are also working on reactors of various sizes,
designs, and physics.
The race is on - and there is a plethora of
companies all seeking to serve the nation's fast-growing demand for
electric energy. The winners may or may not be the first to go
operational but will be the ones whose costs and timelines best fit
customer needs.
|