SECTION V.
BUDGET AND FINANCIAL
5.0 INTRODUCTION
The funding estimates for the Lunar Expedition Program are based on
results obtained from previous concept, feasibility, and preliminary
design studies. These results were published in Lunar Observatory
Final Report, Volume I - Study Summary and Program Plan, numbered
AFBMD TR 60-44 and dated April 1960. The costing of this program was
accomplished by the Rand Corporation and was based on a completely
integrated program.
The funding estimates for the Lunar Expedition represent all the
costs of establishing a habitable facility on the moon except the
cost of developing the Space Launching System.
This funding would include a Lunar Transport Vehicle development
program that would give the US the capability of using the moon and
space. Then if the need should develop in the future, the Lunar
Expedition Facility could be expanded to support military
operations. Studies have shown that the moon possesses real military
potential and it could support a recallable deterrent capability.
The development of the Lunar Transport Vehicle represents a minimum
program for the Air Force to obtain control of the cislunar volume
and the lunar surface.
5.1 BUDGET ESTIMATE AND FINANCIAL
PLAN
A preliminary design for the Lunar Transport Vehicle is
presently being accomplished by six contractors on an active
study program. This program was funded for $300,000 in FY 61 and
three of the contractors are each performing the design under a
$100,000 contract. The other three contractors are participating
on a voluntary basis. The final reports for this preliminary
design will be submitted to the SSD on 30 June 1961. Evaluation
of these reports will follow immediately and the results will be
used to revise this document where necessary The Lunex program
has an Engineering Design competition scheduled for initiation
in January 1962. This competitive effort would be evaluated and
a decision on the manufacturing approach would be possible by
January 1963. To accomplish this program the following funds
will be required:
-
FY 62: $ 26.9 million
-
FY-63: $ 112.2 million
Should the above funds not be made
available, the schedule for establishing the Lunar Expedition
will be delayed proportionally to the delay in funding.
-
Launch Facilities
-
Expedition Costs
5.2 COST ESTIMATES
The funding requirement for the complete Lunex Program are as
follows:
FY COSTS (in millions of
dollars)
Item 1962 1963 1964 1965 1966 1967 1968 1969 1970 1971
R & D 26.9 104 335 660 1084 1608 -- -- -- --
Launch Facilities -- 8 64 64 -- -- -- -- -- --
Expedition Costs -- -- -- -- -- -- 1135 1023 798 631
Annual Total 26.9 112 399 724 1084 1608 1135 1023 798 631
Program Total 7541
To accomplish the Lunex Program,
addition information about the lunar surface is required at an
early date. This means lunar surface photographs from a lunar
orbiting vehicle and the delivery of a radio-light beacon to the
lunar surface by a soft landing vehicle. Present NASA programs
will provide some information and capability. However, to meet
the Lunex program schedule, the following additional funding
will be required by either the NASA or the Air Force:
Unmanned Vehicles - FY COSTS (in
millions of dollars)
Item 1962 1963 1964 1965 1966 1967 1968 1969 1970 1971
Lunar Photographs and Radio-Light Beacon 15 75 85 15 -- --
-- -- -- --
Recovery of Lunar Core Sample 12 35 85 285 265 85 24 -- --
--
Annual Totals 27 110 175 300 265 85 24 -- -- --
5.3 FY 62, 63 FINANCIAL PLAN
ITEM FY-62 FY-63
MANNED LUNAR PAYLOAD
Lunex Re-entry Design & Mock-up
-- (2 cont'r, 8 M ea) 16,000 80,000
Lunar Landing Stage
-- (2 cont'r, 1 M ea) 2,000 10,000
Lunar Launching Stage
-- (2 cont'r, 1 M ea) 2,000 10,000
SECONDARY POWER
Manned Vehicle Power System 600 1,000
Surface Vehicle Power System (15 kW) 100 300
Nuclear Lunar Facility Power (300 kW)
-- (Spur Program Support) 1,000 1,500
GUIDANCE
Mid-course System 200 450
Lunar Terminal System 300 450
Lunar Ascent System 100 300
Earth Return System 200 500
LIFE SUPPORT
Crew Compartment Design 400 1,000
Ecological System 1,000 1,200
Moon Suit or Capsule 500 800
COMMUNICATIONS & DATA HANDLING
Manned Vehicle Video System Design 400 1,000
Wide Band Moon-Earth Link Design 200 400
Secure Narrow Band Link Study 100 300
Man-Man Lunar Surface 300 650
Materials and Resources
Re-entry Materials Research 1,000 1,300
Lunar Natural Resource Dev. 500 1,000
--------------------------------------------------------------------------------
Total In Thousands 26,900 112,150
VI. PROGRAM
MANAGEMENT
6.0 MANAGEMENT FOCAL POINT
The focal point for management of the Lunar Expedition Program will
be a Lunex Program Office within the Space Systems Division, AFSC.
The Director of the Program Office will co-ordinate, integrate,
monitor and direct all activities of the Lunex Expedition Program.
Subordinate to the Director will be managers for major parts of the
program. A tentative organisational chart for the Program Office is
shown in Figure 6-1.
6.1 RESPONSIBILITIES
a. The Earth Launch Complex
Office will be responsible for the civil engineering aspects
of building up the earth launch base. The immediate problem
of this office will be a site selection survey.
b. The Earth Launch Vehicle Office will be responsible for
all earth launch boosters required for this program.
c. The Lunar Landing and Launch Vehicles Office will be
responsible for all development and testing of the Lunar
Landing Stage and Lunar Launch Stage.
d. The Manned and Cargo Payloads Office will be responsible
for the development of the manned Lunex Re-entry Vehicle and
the Cargo Package. This will be one of the key offices in
the entire program since it will be concerned with such
major technical areas as life support equipment, re-entry
problems, secondary power and structures.
e. The Communications and Data Handling Office will be
responsible for establishing the communication network and
centralised data handling organisation. It will also concern
itself with communications problems between the earth, the
moon, and the Lunex Re-entry Vehicle and point-to-point on
the lunar surface.
f. Guidance and Flight Control office will be responsible
for developing: ascent, mid-course, terminal, lunar ascent,
and re-entry guidance equipment.
g. The Lunar Expedition Facility Office block (shown in
dotted outline) indicates that that office will be
established at a later time since the problems associated
with the expedition facilities are not of immediate concern.
h. The Plans Office will be responsible for examining other
potential uses of equipment developed for the Lunex Program.
For example, the same equipment could be used for sending
men around Mars and Venus, or perhaps effecting a landing on
Phobos. Considerable planning also needs to be done
regarding the exploratory phase of the Lunar Expedition.
i. Programming Office will be responsible for scheduling and
budgeting of the entire program. This office will have under
its control a network of computers designated as the PEP
program.
j. The Technical Integration and Support Office will be
responsible for insuring the technical compatibility of all
components of the system, such as, that the vibration is
within tolerable limits during the boost phase when all
components of the system have been put together. This office
will also provide technical assistance to each of the main
component offices. The component offices such as the Manned
and Cargo Payloads Office will not rely entirely on the
Technical Integration and Support Office for assistance, but
will be free to obtain the best technical advice available
in the nation from whatever source is necessary, such as
other government laboratories or universities. This
Technical Integration and Support Office will be manned by
Air Force officers who will be responsible for the various
disciplines and for technical support from the Aerospace
Corporation.
k. The Reliability Office will insure that a strong
reliability and safety program is followed by all
contractors throughout the program. Since reliability and
safety is of such extreme importance in this program every
effort must be made to insure the reliability of the final
equipment. This can only be done by giving proper
recognition to the. problem at a high organisational level
where policies and recommendations can be recognised and
implemented.
6.2 PROGRAM OFFICE MANNING
A Program Office must be established immediately after
program approval if planned schedules are to be met. It is
estimated that an initial build-up to 72 officers plus 35
secretaries will be required. A requirement for 100 MTS will be
established with the Aerospace Corporation. In view of the
magnitude of the program, which will build up to more than one
billion dollars a year, a larger Program Office will be
required. Planning for these increased manpower requirements
will be accomplished by the Program Office, after it is
established. Suggested initial distribution of personnel within
the Program Office is as follows:
a. Lunex Program Director 4
b. Plans 4
c. Programming 6
d. Technical Integration and Support 20
e. Reliability 2
f. Earth launch Complex 5
g. Earth Launch Vehicle 5
h. Lunar Landing and Launch Vehicle 5
i. Manned and Cargo Payloads 15
J. Communications and Data Handling 3
k. Guidance and Flight Control 3
6.3 ORGANIZATIONAL RELATIONSHIPS
There will be a continual and energetic exchange of
direction and information between personnel of the Lunar Program
Office and development contractors. Because of the complex
nature end magnitude of the program, the Program Director will
be required to deal with many contracts from diverse technical
areas. It is envisioned that an associate contractor will be
selected for each major portion of the program, who will, in
turn, use many supporting contractors of various technological
capabilities. Technical integration and support will be
accomplished by the Aerospace Corporation under the overall
guidance and control of the Program Office.
6.4 AIR FORCE DEVELOPMENT AND SUPPORT
The Lunex program office will work with the Technical Area
Managers within AFSC. The Technical Area Managers have project
responsibility for development of solutions to technical
problems such as those associated with guidance, materials,
rocket engine propulsion, life support, etc. Each Technical Area
Manager will identify and emphasise those critical technical
problems to which specific effort must be directed in order to
attain a capability required by the Lunex program.
6.5 OTHER AGENCIES
Specific arrangements will be made with other agencies as
requirements arise in the development of the Lunex program.
6.6 MANAGEMENT TOOLS
The basic philosophy of developing all elements of this
program on a concurrent basis introduces rigid scheduling
requirements. Specific tasks must be defined and scheduled.
However, when development problems dictate that many factors be
varied to keep abreast of advancing state-of-the-art,
concurrency and even the end objectives are affected and
possibly delayed.
A management tool which uses an
electronic computer will be used to support the Program Director
in planning, operating, and controlling the Lunar Expedition
Program. It will be initiated in the early stages of the program
and continue to be used throughout the expedition phase. This
management tool, called Program Evaluation Procedure (PEP) will
assist the Director by providing:
a. A method of handling large
masses or data quickly, efficiently and economically..
b. The capability to locate, identify and this correct
trouble spots.
c. The capability of integrating the many varied and
complicated facets of the Lunar Expedition Program.
6.7 PEP
The PEP management tool is made possible through the use of
an electronic digital computer. The scheduling and monitoring of
many thousands of items required in the Lunar Expedition Program
make the use of this computer technique imperative. The PEP
approach employs linear programming techniques with a
statistical concept in conjunction with the electronic computer.
This procedure facilitates the analysis of interrelationships of
many thousands of program elements. The results are presented as
program summaries upon which the Director can base decisions.
(See Fig. 6-3)
The first step in using the PEP management tool is to make a
detailed analysis of the overall Lunex Program. Each major
event, milestone, or accomplishment that must be achieved is
listed in chronological order. The events must be well defined
and should occur at an instant of time which can be identified.
A network, or a program plan chart, is laid out in which the
events are shown as points or circles whose positions roughly
represent their chronological order. Interrelationships between
the events (circles) and sequence of events are shown by
connecting lines. The line between the events represents work
that must be done to proceed from one event to the next (See
Figure 6-4).
The computer then totals all of the
expected activity times along every possible (in the thousands)
route of the network from start to the end event. The PEP
computer then examines the total times of the large number of
paths in order to find the longest, which is called the critical
path. The critical path defines the sequence of events which
will require the greatest expected time to accomplish the end
event.
The effects of a delay for any particular milestone or event an
the entire program or on any other event can be quickly and
efficiently determined so that corrective action can be taken if
required.
SECTION VII. MATERIEL
SUPPORT
7.0 PRODUCTION
It is intended that this
program use two significant concepts that will result in better
management of the materiel support program. These are the Delayed
Procurement Concept and the Responsive Production Concept. Under the
Delayed Procurement Concept, the ordering and delivery of high-cost
insurance-type spares is deferred until the final production run
must be made, allowing for the accumulation of maximum operational
experience with the new item before a final spares order must be
placed. Under the Responsive Production Concept, a portion of the
requirement for high-cost operational spares is procured in
unfabricated, unassembled form.
When the spares demand can be more
reliably predicted, based on actual usage experience, additional
complete spare items can be produced within a very short lead-time
period. When experience fails to justify a requirement for
additional complete spares, the materiel and parts involved can be
utilised in end article production. The policy shall be to buy
minimum quantities of high-value spares and maintain close control
over their transportation, storage, issuance, and repair until they
finally wear out, or are no longer required. Simplification of
procedures and relaxing of restrictions on low-value items will
provide the means (man-power, machine time, etc.) for more precise
management of high-value items.
7.1 SUPPLY
Maximum utilisation will be made of existing assets. Where
practical, equipment and parts will be reclaimed from completed
test programs, repaired, modified and overhauled to suitable
condition for use in later tests and operational tasks. The
procedures and paperwork involved with procurement of spare
parts must be streamlined to permit maximum flexibility in
planning and responding to a continually changing configuration.
Immediate adjustment of inventories and reorder points must
result from test program and engineering changes. Selection of
spare parts should be made at the time of initial design to
enable procurement of spare and production parts concurrently to
eliminate reorder costs resulting from separate procurements.
Determination of quantities, reparable-overhaul modification
planning, control etc., shall be accomplished and directed by a
permanently organised and active group composed of personnel
representing the engineering, production, materiel, reliability,
quality control, procurement and contract departments, and the
various affected sections within these departments such as
design, test, planners, etc., attending as required. The AFPR
will have a member assigned to this group for surveillance
purposes and to provide logistic guidance on problems which may
require advice from the Air Force.
Persons assigned to the group shall be well qualified by reason
of experience and technical ability.
The procedures and paperwork involved shall be streamlined,
taking due cognisance of the powers and capabilities of the
above group to permit maximum flexibility in planning and the
quickest possible response to changes and emergency situations.
The group will pay particular attention to control of hi-value
items and items critical to the needs of the expedition and test
program. Such items, particularly those potentially subject to
imminent redesign, will be rigorously screened to assure
economical inventory and the best possible repair, overhaul and
modification planning at all times.
The group shall be responsible for the following:
a. Immediate adjustment of
inventory and reorder points resulting from changes to the
delivery schedule, the test program, and for engineering
changes.
b. Inventory review and adjustment of initially established
stock levels and/or reorder points in light of latest
experience gained from the test program every time reorder
or minimum stock levels are reached.
c. Review of stock levels, and adjustment or disposition of
non-moving items on a continuing basis, but at intervals not
to exceed sixty (60) days for any individual hi-value items
and 180 days for other items, or at other internals as
agreed upon by the Contractor and the Contracting Officer.
This is to include the return to production of any surplus
quantities for rework to later design requirements.
d. Control of repair overhaul modification planning.
7.2 DISTRIBUTION
The Contractors shell develop internal working procedures
which encompass the following requirements:
a. Inventory levels shall be
programmed to vary with anticipated utilization. Shipments
in advance of estimated requirements will not be made except
when it is clearly in the best interest of the program to do
so.
b. Stock levels shall be minimised by maximum economical
reliance on repair, overhaul, and modification of reparable
items. Repair, overhaul, and modification turn-around time
will be a prime determinant in establishing the minimum
stock level period for each item.
c. Where feasible (with particular emphasis on hi-value and
critical items), inventory cost will be minimised by
stockage of repair, overhaul and modification spares, pieces
and components (relatively low-cost items) in conjunction
with a pre-planned and flexible expedited repair, overhaul,
and modification program, as opposed to stocking
sub-assemblies and end items themselves (the relatively
high-cost items).
d. Stock levels will be determined on basis of overall
program needs and will be independent of the site location
of the stock. Maximum utilisation will be made of available
contracted air transportation to minimise "pipeline" time.
7.3 STORAGE
Parts, whether required for the test or expedition programs,
should not be segregated from production stock. This merely adds
an unnecessary stockage cost burden. By combining storage
facilities with a commingling of stock, considerable cost
savings can be effected. Spares and production stock serve as
buffer stocks for each other. If multiple activities such as
manufacturing, test, and the expedition are supplied from a
single storage facility the chance of stock-out would be
minimised.
7.4 REAL PROPERTY INSTALLED EQUIPMENT (RPIE)
Each contractor is charged with the responsibility of
identifying, as well as determining the criteria for all items
required for successful mission accomplishment. When the
requirements have been determined the responsibility for
accomplishing the required RPIE materiel support program will be
assigned. This materiel support will include the necessary
selection of spare parts to be stored at the manufacturing
facility or at the launch site.
7.5 MAINTENANCE
The proposed operational mode of the Lunex program is unique in
that it retains all the features of a research and development
program. In the time period designated as "expedition", it can
be expected that in addition to a variety of missions the
systems will be modified and improved, the launch facilities and
support equipment may require modification, and technical
development may force program changes. Since the expedition
period is actually a continuation of the development and test
program it is apparent that the systems and techniques developed
during testing may also be continued for the Expedition.
An evaluation mill be made to determine the feasibility of
having contractors support the program throughout its entire
life. However, in determining the total task, consideration must
be given to the available Air Force manpower, equipment and
facilities that may be used to support the Lunex program.
7.6 MANUFACTURING FACILITY CRITERIA
The equipment production facilities will preferably consist
of an existing large aerospace plant convertible to Lunex
production with a minimum modification program. It may be
necessary to build a faculty that is adjacent to, or easily
accessible to navigable waterways. The facility should obviously
be located in an area containing an abundance of skilled
manpower. Manufacturing Test Facilities adjacent to the
manufacturing facilities would be very desirable to reduce
transportation problems.
Certain items, such as the large liquid and solid boasters and
propellant, will probably be assembled at the Lunex Launch
Complex and special facilities for manufacturing these items
will be required at the launch complex. Thus checkout and
acceptance test facilities will also be required at the launch
complex.
Many major manufacturing items, such as the Lunar Landing Stage
and the Lunar Launch Stage, will be produced at the
manufacturers' facility. This will require propellant storage,
or a propellant manufacturing capability at the plant, plus
various test and check-out facilities to support manufacturing.
As an example, the following test facilities will be required to
support the manufacturing of the Lunar Landing and Lunar
Launching Stages:
a. Configuration
-- For each of the two stages a
Propulsion Test Vehicle Test Stand and two Flight Acceptance
Firing Stands will be required. In addition, cold flow test
facilities consisting of one pad and three structural towers
will be required.
The separate test complexes will dedicated one for each of
the two stages. There will be only one centrally located
blockhouse with control and instrumentation capability for
operating both complexes. Each hot firing stand would be
located in accordance with a 2 psi explosion overpressure
criteria. An explosive force calculated on equivalent LH2
caloric content to TNT, shows that the hot stands should be
no closer than 2000' to any other hot or cold stand.
b. Test Pad Configuration and arrangement
-- Each hot test pad will
consist of a concrete pad containing the launcher structure.
The stage is erected by a mobile commercial type crane, and
personnel access for maintenance is by work stand and
ladders, or a cherry picker. No service tower will be
required.
c. Thrust Level Measurement
-- Thrust levels will be
determined by measuring the chamber pressure and applying
the result to the engine manufacturer's calibration curve.
Tanking level is determined by the Propellant Utilisation
System.
d. Altitude Simulation Unit
-- A plenum chanter, containing
steam jets upstream of its exhaust bell, shall be attached
to each engine for altitude simulation.
e. Flame Deflector
-- The design is a conventional
configuration elbow shaped shield cooled with a firex water
injection system.
f. Propellant Storage and Handling Equipment
-- A central LO2
storage and transfer facility shall be provided for each of
the two test facilities. The Lunar Landing Stage facility
shall store 350,000 lbs. of LO2. Spherical,
vacuum insulated dewars shall be used. The transfer unit
shall be a motor operated centrifugal pump with 500 gpm and
100 psi discharge head capacity. The Lunar Launch Stage Test
Facility LO2 storage shall contain 18,000 gallons
in spherical dewars with a transfer pump capability of 200
gpm and 100 psi discharge head. Distribution lines for both
complexes would be prefabricated, static vacuum, insulated
steel pipe.
An LH2 storage and transfer facility will be
provided at each hot firing test stand and the cold flow
test pad. The transfer system is an LH2 gas
generator system with air being the thermal source.
Pressuring level in each tank would be 100 psi. The LH2
storage capacity requirement for each Lunar Launch Stage
facility is 15, 000 lbs. and at each Landing Stage Site is
35,000 lbs. Again the storage facilities would be spherical
dewars with segmented, prefabricated, static vacuum
insulated stainless steel pipe distribution lines.
VIII. CIVIL
ENGINEERING
8.0 INTRODUCTION
As part of the Lunar
Transport Vehicle study, consideration was given to the facility
required for the launch and support of the Space Launching System
and the lunar payloads. It was assumed that the manufacture of all
boosters and the payload would be accomplished at existing
factories. Facilities and equipment required for the manufacture of
large boosters may be readily installed at factories having
clearance sufficient to handle the booster. Large boosters such as
required for this program must necessarily be transported over long
distances by specially constructed barges. By selecting
manufacturing facilities and launch sites adjacent to navigable
waters, a minimum of overland transport would be required. A
significant saving may be effected by providing launch capabilities
at selective areas where existing support facilities, personnel
housing, and assured tracking capabilities are available.
The logistic support for the launch rates indicated in this plan
dictates that new propellant manufacturing facilities be constructed
at the launch site and that transport barges and other vehicles be
available to transport vehicle components from the manufacturing
plants.
A modified Integrated Transfer Launch System is envisioned for the
Lunar Transport Launch System. The size and weight of the Space
Launching Vehicle, designated the BC2720, precludes the transfer of
the entire Lunar Transport Vehicle after assembly, but the
integrated transfer of upper stages and lower stages separately with
a minimum mating and checkout on the launch pad may provide
increased reliability and appreciable cost saving.
In order to achieve the highest launch pad utilisation possible and
to make maximum use of specialised capital equipment and highly
skilled manpower, the application of operations research technology
will be required. To handle the test load and the complex sequencing
requirement presented by the three-stage Space Launching Vehicle
plus the Lunar Payload, a computer controlled, integrated launch
sequencing and checkout system will be needed. It is desirable to
accomplish the maximum amount of systems testing in a protected
environment prior to locating the vehicle on the launch pad, and to
use the launch pad, in so far as is possible, for its prime purpose,
that of pre-flight servicing and launching the vehicle.
8.1 LUNAR LAUNCH COMPLEX
The lunar Transport Vehicle
System has a requirement for launch and support facilities suitable
for manned lunar flight of a vehicle using a BC2720 Space Launching
System. Investigation of the launch pad requirements for a launch
rate of two per month indicates that from 4 to 6 launch pads would
be necessary depending on the launch site location and the means
available for handling the booster. There are no existing launch
pads capable of handling this vehicle, nor are there, at this time,
facilities capable of conducting static testing of the "C" boaster
and the launch of the complete Lunar Transport Vehicle. It is
possible that by combining the capabilities for both static firing
and launch in two of the pads required, a significant cost saving
may be gained and an accelerated test program may be effected. This
would provide a capability for the launch of the "C" booster with or
without solid boost during R&D flight test and for early test
missions of the Lunex Re-entry Vehicle. The development and flight
test of the "B" booster is planned at AMR during the development
program.
It was assumed in the Lunar Transport Vehicle study that the
manufacture of all boosters and the payload would be accomplished at
existing factories. New and added facilities and equipment such as
large forming brakes, special welding jigs, fixtures and machines,
and large processing facilities would be required. In plants of
sufficient size these facilities and equipment could readily be
installed. Further investigation comparing the relative economics of
manufacture at the launch site versus manufacture at existing
facilities is required to insure an economical choice.
Assemblies having a diameter exceeding 12 feet or weighing over
200,000 pounds cannot be transported over United States railways. A
load of 78,000 pounds is considered to be the limit over selected
highway routes. Inasmuch as both the "B" and "C" boosters of the
Space Launch Systems have diameters in excess of 14 feet, transport
from manufacturing plant to the launch site must be by barge. The
large quantities of boosters and the special environmental
protection required suggest that specially designed barges be
constructed to transport these assemblies. Harbours and docking
facilities would be required near the manufacturing facility and at
the launch site.
By locating the launch facilities at or near Cape Canaveral for an
easterly launch significant savings may be effected. The use of
existing administrative capabilities, personnel housing, assured
tracking facilities, and technical support areas will provide a
saving in costs and in lead-time required for construction of
support facilities. Similar gains may be made by locating launch
facilities at Point Arguello for polar launch. This does not mean
that Cape Canaveral and Point Arguello are the only reasonable
locations for the launch site. In fact, by extending the Atlantic
Missile Range in a westerly direction across the Gulf of Mexico it
is conceivable that a launch site in the vicinity of the Corpus
Christi Naval Air Complex would provide the full use of AMR Range
facilities with minimum overfly of foreign land masses. Likewise,
extension of the AMR Range in a northerly direction to the coast of
South Carolina would provide a similar accommodation.
8.2 LOGISTICS
The logistic support for the
launch rate as indicated in this study dictates that new propellant
manufacturing plants be constructed at the launch site. Existing
propellant manufacturing plants are inadequate and the launch rates
mentioned would use the full capacity of a separate propellant
manufacturing facility.
a. Propellant use rates for a 2 per month launch rate are estimated
as follows:
(1) Liquid Hydrogen manufacture:
50 tons per day.
(2) Liquid Hydrogen storage at launch pad: 1.5x10^6 pounds.
(3) Liquid Oxygen/Nitrogen Manufacture: 120 tons per day.
(4) Liquid Oxygen storage at launch pad: 4 x 10^6 pounds.
Barges will be required for transport of
boosters from the manufacturing plant to the launch complex.
8.3 AEROSPACE GROUND ENVIRONMENT
A modified Integrated Transfer
launch System is envisioned for the Lunar Transport Launch System.
This is approach would allow the complete integration and checkout
of the "B" booster together with the Lunar Transport Payload in a
protected environment simultaneously with the assembly and checkout
of the C2720 booster combination at the launch pad. The size and
weight of the BC2720 Space Launching Vehicle precludes the transfer
of the completely assembled Lunar Transport Vehicle from an
integration building to the launch pad. It is feasible, however, to
mate and integrate the "B" booster with the Lunar Transport Payload
inside the protected environs of an integration building and when
completed transfer the "B" booster and payload assembly to the
launch pad for mating with the C2720 assembly. See Figures 8-1 and
8-2).
This can best be accomplished by a
cliff-side location or extending a ramp from the integration
building to an elevation at the launch pad approximately equal to
the height of the C2720 stage. The assembly and checkout of the
C2720 vehicle may be accomplished in two ways depending on the
specific location of the launch pad and its accessibility to
navigable waters. For a launch pad having no direct access to
navigable waters, the assembly and mating of the solid segmented
motors to the "C" booster would be accomplished at the launch pad.
The extended time necessary to accomplish this assembly and checkout
accounts for the difference in the numbers of pads required. It is
estimated that 6 launch pads would be needed for this plan.
For a launch pad having direct access to
navigable waters, the assembly and mating of the solid segmented
motors to the "C" booster could be accomplished at an interim
integration building located some distance away from the launch pad.
After assembly and checkout, the "C2720" combination would be
transported by a barge to the launch pad and mated to the "B"
booster and payload assembly. By Using this approach it is estimated
that 4 launch pads would be adequate for the 2 per month launch
rate. Final confidence checks and integration of the booster and
facility interface would be accomplished at the launch pad.
The TNT equivalent of vehicle propellants was estimated in the
following manner. The TNT equivalent of the liquid propellants was
taken at 60% of the total LOX/LH2 load for all stages. This is the
figure currently used at AMR for TNT equivalence for LOX/LH2. In
this case, because of the great quantities of propellant involved,
this degree of mixing is unlikely and the 60% figure would be
conservative. Solid propellants are taken at 100% of the propellant
weight. It is also considered that detonation of the solid
propellants may cause the subsequent detonation of liquid
propellants and vice versa; but, the simultaneous detonation of all
propellants is not likely to occur.
This philosophy resolves to
consideration of TNT equivalents of liquid propellants and solid
propellants separately and they are not additive. The TNT equivalent
of one of the four segmented solid assemblies is 680,000 pounds. The
60% TNT equivalent of the total liquid propellant load is
approximately 1,300,000 pounds. Using the highest TNT equivalent
(1,300,000 pounds) the inhabited building distance must be
approximately 2 1/2 miles from the launch pad and minimum pad
separation must be approximately 1 mile. For an inhabited pad
adjacent to a launch operation, pad separation would be 2 1/2 miles.
It is obvious that the real estate problem will be extensive.
For a coastal location of "C" launch
pads up to 18 miles of continuous coast line would be required for a
distance of 3 miles inland. These distances can be decreased by
creating a buffer between the pads. Locating the launch pads in
ravines or indentations in cliff aide launch locations might
substantially reduce the land areas required. The selected location
and orientation of the integration building and other support
facilities to take best advantage of topography would do much to
decrease distances and reduce costs.
The repeated launching of similar payloads in the Lunar Transport
Launching System and the extended time between launches from each
pad indicates that a central launch control for all pads might be
desirable. To avoid analogue signal line driving problems and to
allow greater distances than normal between the pads and the common
blockhouse it is possible to use digital control for launch pad
checkout and launch.
Analogue to digital conversion would
essentially be accomplished at each launch pad and transmitted to
the blockhouse via digital data link. With vertical mating, assembly
and detailed checkout in the vertical assembly integration
buildings, only gross, survey type testing or a simulated countdown
and launch would be performed at the launch pad, since test and
vehicle subsystem sequencing systems could be installed in both
areas. Present day checkout methods, because of the many manual
controls and long time spans involved, would not provide sufficient
assurance of the high reliability of the complex integrated systems
expected in the Lunar Transport Vehicle.
SECTION IX.
PERSONNEL AND TRAINING
9.0 INTRODUCTION
This section of the Lunar Expedition Program Plan (Lunex) includes
estimated personnel requirements to support the program and presents
the training required to accomplish the end objective.
The personnel requirements were derived on the basis of the scope of
the complete program and the personnel would be comprised of
civilian and military personnel. .
The training program was prepared by the Air Training Command and
based on the Lunar Expedition Program Plan.
9.1 PERSONNEL
The accomplishment of the Lunar Expedition Program will have a
manpower impact on the Air Force that is quite different than
previous programs. The number of personnel actually on the
expedition will be relatively small compared to the number of
personnel required to support the operation. The actual contractor
"in-plant" personnel required to accomplish this program are not
included in the following figures. However, a general estimate of
the total contractors' effort, based on the average estimated annual
expenditure for the complete Lunex program, would be the equivalent
of one of our larger manufacturing companies with 60 to 70 thousand
personnel. It should also be stated that this effort would
undoubtedly be spread throughout the industry and not concentrated
in one company and the previous statement is only for comparison.
The military and civilian personnel required to support the Lunex
program is estimated as follows:
Space Personnel: 145
Lunar Expedition (21 men at expedition facility, crew rates
of 5): 145
Ground Personnel: 3677
Lunar Squadron: 100
Launch Squadron: 873
Instrumentation Squadron: 293
Assembly & Maintenance Squadron: 860
Supply Squadron: 562
Base Support Units: 639
Administration: 350
Total Direct Personnel (Space plus Ground): 3822
Overhead: 1287
Range Tracking: 940
Logistic Support Organization: 347
Grand Total Personnel: 5109
9.2 TRAINING PROGRAM
The remaining portion of this section of the Lunar Expedition
Program Plan (Lunex) presents the Training Program. It is based on
the limited data and information available at the time of
preparation. The knowledge gained from the state-of-the art
development of this program will of necessity have to be applied
directly to the training areas to insure "concurrency" of the
programs training development. Further, the training knowledge and
experience acquired from current research and development programs
must be studied for application to this program.
The concepts and plane projected in this part of the PSPP will be
subject to constant revision and/or updating. Use of various
simulators and synthetic training devices must be a part of the
training program. Identification of the required training equipment
and real property facilities to house them must be accomplished
early in the program development to insure training equipment and
facilities being available to meet the training need dates.
The unique mission of the Lunex program requires a comprehensive and
timely source of personnel equipment data (PED). This information is
required for space crew end support positions required to operate
and maintain the space vehicles and support equipment. Development
of such data must be initiated as part of the design effort to
reduce the time element for follow-on personnel sub-system
requirements.
No effort is made in this section to specify requirements for the
Space Launching System since they are delineated in the Space
Launching System Package Program.
This section of the Proposed System Package Program was developed
under the premise that Air Training Command would be assigned the
individual aerospace crew and technical training responsibilities
for this program. Therefore, ATC must develop their capability
concurrent with hardware development through the engineering design
phases to support the expedition.
9.3 PLANNING FACTORS AND GROUND RULES
a. Scope:
This section is conceptual in nature
at this time and embodies the basis for the training to be
accomplished in support of the Lunar Expedition Program. It
includes guidance for individual, field unit, and crew training.
b. Definitions:
(1) Aerospace Crew Personnel:
Personnel performing crew duty in the Lunar Transport
Vehicle.
(2) Cadre Personnel: Those personnel necessary for logistic
planning, AFR 80-14 Testing Programs, and ATC instruction
and preparation of training materials. The requirements for
participation in the testing programs will include test
instruments for category testing in accordance with
paragraph 5 a (1) and (2), AFR 80-14, and Job Training
Standards for the Integrated Systems Testing Program in
accordance with paragraph 8 g (3), AFR 80-14.
(3) Main Complement Personnel: Personnel employed in the
receipt, check-out, installation, repair, maintenance and
operation of the system.
(4) Support Personnel: Air Force Logistic Commend personnel
required for support functions as well as other agencies'
supervisors and planners
(5) Types of Training:
(a) Type I (Contract Special
Training). Special training courses conducted by
contractors at an ATC installation, contractor facility
or any other designated site.
(b) Type II. (ATC Special Training) Special Training
Courses conducted by ATC training centres' instructors
at an ATC installation, contractor facility, or any
other designated site.
(c) Type III. Career training/
(d) Type IV. Special training provided by ATC training
detachment instructors at the site or the organisation
requiring the training.
(6) Testing Programs:
(a) Component - the testing
of the components of a sub-system, such as the guidance
package, or ecological package.
(b) Sub-system - components assembled into a sub-system,
such as the Re-Entry Vehicle Subsystem and tested as a
unit.
(c) Integrated System - the Re-Entry Vehicle, Lunar
Launching Stage and Lunar Landing Stage assembled
together and tested as a whole system.
c. Assumptions
(1) The man-rated Lunar
Transport Vehicle will be available for use by the Lunar
Expedition in 1968.
(2) ATC personnel will observe, participate and study the
training programs developed for current research and
development programs conducted under other government
agencies and/or contractors.
(3) AFR 80-14 will be used as a guide for accomplishing the
program testing.
(4) The terminology for normal levels of maintenance, i.e.,
organisational, field, depot, and shop, vehicle assembly and
maintenance as specified in AFLC (AMC) letter MCM, dated 25
July 1960, subject: Standard Maintenance Terms and
Maintenance Facility Nomenclature for Missile Weapon Systems
will apply.
(5) The Air Force Maintenance policy of maximum maintenance
at the lowest feasible level will prevail.
(6) Due to the time phasing of the subsystems, special
consideration must be given to the training facilities
requirements funding for the Re-Entry Vehicle technical
training programs.
(7) Testing Dates:
(a) Start of Component
Testing Dates are:
1. Re-Entry Vehicle -
June 1963.
2. Lunar Launch Stage - February 1965.
3. Lunar Landing Stage - May 1965.
(b) Start of Subsystem
Testing Dates are:
1. Re-Entry Vehicle -
November 1964.
2. Lunar Launch Stage - May 1966.
3. Lunar Landing Stage - July 1966.
(c) Peculiar Requirements
and/or Limitations:
(1) The unique mission
of this program makes it mandatory that the
following actions be accomplished concurrent with
the development of the hardware:
(a) The contractors
will develop the Personnel Equipment Data
information concurrent with the design of the
hardware. This is information must be available
to ATC personnel for early planning purposes.
(b) Type I training dates reflected in the time
phasing chart will require the use of R&D and
test equipment as training equipment.
(c) Production schedules for R&D and Expedition
equipment will include the training equipment
required to support Type II and Type III
training. Allocation and delivery priorities
will be in accordance with AFR 67-8.
(2) An identification of
personnel necessary to support this system has been
made in order to assist in defining the training
parameters. Changes to these estimates will he made
as more conclusive information becomes available.
See Charts IX A and B.
(3) Maximum Cross-Training will be provided as
required to all personnel associated with this
program.
(4) The requirement for follow-on training and the
value of past experience is recognised and maximum
retention of personnel is mandatory.
(5) New and peculiar training problems are
envisioned for the technical personnel
(6) The training of the aerospace crew personnel
will require the development of a program which is
unique to the Air Force.
(d) Qualitative and
Quantitative Personnel Requirements Information
(1) A QQPRI prepared in
accordance with Mil Spec 26239A will be required to
develop the training courses, course material and
substantiation for the Personnel Classification
changes.
(2) ATC and other applicable commands will furnish
personnel for the QQPRI integration team and provide
technical guidance to the contractor during
preparation.
9.4 TRAINING
a. Training Responsibilities and
Concepts:
(1) Engineering Design Effort
(a) ATC will participate in the engineering design effort to
insure that technical data is collated with the personnel
sub-system for follow-on training program requirements.
(b) ATC will be responsible for training required in
support, of the R&D effort under AFR 50-9.
(c) Selection of the initial aerospace crew personnel and
ATC aerospace crew training instructors for the Lunar
Transport Vehicle will commence 8 months prior to the start
of Category I Testing.
(d) All Lunar Transport Vehicle crews and military space
launching support personnel will be phased into special
training (Type I), 6 months prior to Category I Testing.
(e) Environmental, space training for the selected crews and
instructor personnel will start 9 months prior to the start
of Category II testing and will be conducted by the
Aerospace Medical Centre, Brooks AFB, Texas.
(f) ATC Lunar Transport Vehicle crews will be phased out of
training 30 days prior to the requirement for Type II or III
aerospace crew training to provide follow-on training
capability in this area.
(2) Flight Testing & Expedition Program
(a) ATC will be responsible for all individual training,
i.e., technical, aerospace crew, AGE and addition job tasks
as required.
(b) All requirements for Type I Special Training, AFR 50-9,
in support of this effort will be contracted for by ATC.
(c) ATC will maintain liaison with the contractor concerning
engineering changes in the program during its development to
keep trainee information in consonance with the program /
sub-program configurations and other concepts having a
direct implication to training.
(d) Flight Testing & Expedition Crew proficiency will be the
responsibility of the Lunex Program Director unless ATC is
requested to furnish this training.
9.5 TRAINING PERSONNEL
a. Field Training Detachment
(FTD)
The number of personnel required to provide training for lunar
vehicle personnel will be determined during the training
programming conference. QQPRI, TPR's, Personal Plan, Operational
Plan and Maintenance Plan will be available at this time.
b. Contractor Technical Service Personnel (AFR 66-18)
Contractor technical service personnel may be initially required
to augment Field Training Detachment (FTD) personnel. CTSP
requirements in support of this program will be phased out as
blue suit capability is achieved.
c. Trained Personnel Requirements (TPR)
TPR will be developed by commands concerned upon approval of
QQPRI, and will be tabulated as gross requirements by command,
by AFSC, and by fiscal quarter. These requirements will be
phased on anticipated need dates for personnel to be in place at
the testing sites, launch sites, and maintenance areas, and will
be furnished Hq ATC in sufficient time to allow proper planning
for required training.
9.6 TRAINING EQUIPMENT PACKAGE
a. General:
Training equipment requirements will be developed to
support:
(1) Check-out and ground
maintenance to be performed by the direct support personnel
for the Lunar Transport Vehicle.
(2) Flight test operations and maintenance to be performed
by the responsible crews. In consideration of this, present
and near future systems experience gained in the aerospace
area will be applied to the Lunex program to assist in the
identification of training equipment. The training for this
program must be conducted in the most realistic environment
practicable.
(3) Post mission maintenance and test equipment.
b. Equipment Selection:
Selection of training equipment will be based on the
following general rules:
(1) Maximum utilisation will be
made of training equipment programmed for other missile and
space system training programs.
(2) During the initial phases, equipment programmed for
test, development, and the expedition programs will be used
to the maximum extent practicable when regular training
periods can positively be scheduled in the use of that
equipment' The lack of availability of such equipment will
result in degradation of training.
(3) Equipment selection will be made in consideration of
future and/or subsequent programs to provide maximum
training capability in similar systems with minimum cost.
(4) Maximum use and development of training films, training
graphics, and synthetic training aids and devices will be
made to reduce requirements for critical operational items
during the initial phases of the program.
(5) Training equipment will be identified in sufficient time
to enable procurement and delivery in advance of equipment
for use in the flight test and expedition program.
c. Planning Factors:
Planning factors for determination of Training Equipment
Requirements:
(1) In view of the limited
program information presently available, definitive planning
factors upon which over equipment requirements may be based
cannot be provided. However, for preliminary planning, the
following factors may be applied to subsystems of the
program to determine order of magnitude. Provided Control
Centres used for other space vehicles will be applicable to
the Lunar Transport Vehicle, Category I (Trainers), Category
II (Parts / Components / End Items), and Category III
(Training Aids / accessories) training equipment
requirements as specified in USAF letter dated 30 January
1961, subject: Weapon System Training Equipment Support
Policy will be as follows:
Major Vehicle Sections:
Percent of Sub-System Cost Required for Training Items
(a) Re-entry Vehicle: 250%
Complete R/V - 1 ea
Sub-systems of R/V - 1 ea
Major components of each sub-system for Bench Items - 1
ea
(b) Lunar Launch Stage: 150%
Sub-systems of Launch Stage - 1 ea.
50% of Major Components for Bench Items
(c) Lunar Lending Stage: 100%
Major Components - 1 ea
Cargo Package: 100%
Complete Cargo Package
(e) Aerospace Ground Equipment: 200%
Complete set for handling and testing vehicle sections
and included equipment
Complete set as bench items for maintenance training
(2) Training films and
transparencies requirements will be developed as soon as
possible.
(3) Spare parts support will be required for all Category I
and II training equipment.
(4) A continuing requirement will exist for the modification
of training equipment. These modifications should be
provided by review and processing of training equipment
change proposals concurrent with operational equipment
charge proposals.
(5) Funding of P-400 money will be omitted in consonance
with AFR 375-4, Para. 12.
9.7 FACILITIES
a. General:
The needs for training facilities should be established
approximately three years prior to the dates at which Type II
training equipment will be required. Facilities must incorporate
sufficient flexibility to accommodate future updating of
training equipment resulting from program configuration changes.
b. Aerospace Crew Training Facilities:
(1) Initial training for
aerospace crew personnel will require the use of existing
space training facilities. Joint Use Agreements between NASA
and other USAF agencies and the Air Training Command will be
required to insure maximum utilisation of these facilities.
Aerospace Medical Centre's facilities (Brooks AFB, Texas)
will be utilised to the fullest. Interservice agreements
with the Navy for use of specific training device facilities
should be considered for crew training.
(2) The establishment of a centralised space training
facility would have a direct bearing on the overall specific
requirements for this type of training. The results of the
System Study Directive (SSD) Nr 7990-17610, titled: "Centralised
Space Training Facility," will have direct bearing on the
posture of the training facilities of the future. For this
reason, facilities requirements for follow-on training are
not projected.
c. Other Training Facilities:
It is anticipated that Technical Training Centres now in
existence can absorb the additional technical training load
without increasing the facilities. However, modification of
existing facilities to provide training laboratories with
specialised power and environmental systems will be necessary.
This requirement must be identified in sufficient time to permit
facility programming through normal procurement cycles.
9.8 BUDGET AND FINANCE
a. Training Equipment Costs
Funding will be required for training equipment identified
in Section 9.6, Training Equipment Package.
b. Training Facilities Costs
Funding and costs of training facilities will be determined
once the decision is made whether to build a Centralised Space
Training Facility or to continue with decentralised procedures.
Funding can then be determined for the required facilities and
modifications.
CHART IX-B
LUNEX/SPACE LAUNCHING SYSTEM
1. The estimates for the launch system are not included in view of
the status of the Space Launching System (SLS) study. It can,
however, be estimated that the launch complex personnel utilised in
both the liquid/solid propellant type boosters will be integrated
into a team for support of this system.
2. At such time as the S.L.S. is designated as the primary launch
support system, a PSPP will be made for the launch vehicle and
support AFSC's as a part of this program.
SECTION X.
INTELLIGENCE ESTIMATES
10.0 INTRODUCTION
The purpose of this section of the program plan is to estimate the
foreign threat in terms of technical capabilities and probable
programs which may affect the establishment of a lunar expedition.
The threat will be defined in terms of major performance capability
and dates of operational availability.
10.1 Foreword
The following data was
obtained from DCS/Intelligence, Hq ARDC, and published intelligence
estimates.
10.2 PERFORMANCE CAPABILITY
The Soviets have flown geophysical and component equipment payloads
on their vertical rockets for the development, modification, and
acceptance testing of instrumentation for use on their satellite and
lunar aircraft. They developed and used complex scientific
instrumentation on Sputnik III, and stabilisation, orientation and
control equipment on Lunik III and Sputnik IV. Presently, by using
their vertical rockets, the Soviets are testing infrared equipment,
in addition to collecting data on the background noise level of the
earth's surface. It is believed that a development program exists
which eventually could lead to detection and reconnaissance
satellites. The development program which led to the photographic
system used in Lunik III is expected to continue, with an eventual
application in photographic reconnaissance and weather satellites.
The Soviet space launch capability is shown in the following table
of Sputnik and Lunik booster thrust levels:
-
Sputnik I: 300,000 pounds
-
Sputnik II: 300,000 pounds
-
Sputnik III: 432,000 pounds
-
Lunik I, II, and III: 456,000
pounds
-
Lunik IV, V, and VI: 466,600
pounds
There is also evidence of a cluster of
five 140,000 pound units. The Soviets are developing engines of 1 to
2 1/2 million pounds thrust. The estimated time for a booster to
match this engine is as follows:
In general, it takes approximately half
the time for development required in the US
The maximum Soviet orbit capability, with present ICBM boosters
using five (140,000 pound thrust) engines and four (6,600 pound
thrust) engines is 10,000 pounds in low altitude orbit. All Lunik
and Sputnik vehicles utilised a third stage having 12,500 pound
thrust engine burning for approximately 420 seconds.
By using higher energy chemical propellants in modified upper
stages, the payload can be increased up to 15,000 or 20,000 pounds
during 1961. However, approximately 50,000 pounds of payload may be
attained by 1962 if ICBM launch vehicle thrust is increased.
In the 1965-1970 period, a new clustered chemical booster should
allow the Soviets to place 50 to 100 tons in orbit in individual
launches. This will permit landing a man on the moon.
10.3 SUMMARY AND CONCLUSIONS
Very early the Soviets realised the propaganda value obtainable from
space adventures and, accordingly, have striven continuously for
"firsts". This has apparently influenced the detailed pattern for
their space planning. Even though the Soviets have achieved "firsts"
in:
1) Establishment of an
artificial earth satellite
2) Rocketing past the moon and placing a vehicle into a
solar orbit
3) Hard impact on the moon
4) Photographing the side of the moon not visible from the
earth
5) Safely returning mammals and men from orbit
It seems obvious that the Soviet
attempts to score "firsts" will continue.
Although large orbiting spacecraft appear to be the prime Soviet
technical objective during the period of this estimate, it is
believed they will continue to use and improve their current lunar
probe capability since there are many "firsts" yet to be
accomplished in the exploration of the moon. These include lunar
satellites, lunar soft landings, lunar soft landings and return with
actual samples of the lunar surface, and, finally, a tankette for a
true lunar exploration.
It is expected that the Soviets will continue to launch unmanned
lunar rocket probes for the purpose of reconnoitring the moon and
near moon environment for the application of this knowledge to the
development of manned lunar exploration systems.
Since soft landings are essential for obtaining data on the lunar
surface, it is believed that the Soviets definitely will have to
develop techniques for achieving lunar soft landings, especially
soft landings and return to earth, to establish the procedures to be
employed in accomplishing the main objective of establishing a
manned lunar station. The first of these test vehicles could be very
similar to their Arctic automatic weather stations that presently
are jettisoned from aircraft. This vehicle would be able to record
temperature, micrometeorite impact, various types of radiation,
particle concentration, seismic disturbances, solid resistivity, and
depth of probe penetration. As landing techniques are improved,
larger payloads with increased instrumentation for terminal control
and lunar restart and launch capabilities will undoubtedly be
developed.
Circumlunar flights by manned space vehicles, and eventually lunar
landings, will be required in order to know more precisely the
environmental situation preliminary to the eventual establishment of
a lunar base and the complete conquest of this body. This is
considered to be a more distant objective of the Soviet program and
its attainment will appear, if at all during this decade, toward the
end of the period.
Although the landing of a "tankette" on the moon falls under the
category of a soft landing, the size and weight of such a vehicle
makes it a sufficiently worthy subject for special consideration.
The Soviets have published extensively on such a vehicle, and Yu D.
Khelbtsvlch, Chairman of the Science Technical Committee for Radio
Remote Control of Cosmic Rockets, has published his preliminary
design of a tankette laboratory for lunar exploration. Graduate
students of Moscow High Technical School now are experimenting with
models of a tankette in layers of powdered cement to simulate
powdered soil conditions which might be expected on the moon.
Actual accomplishment of the project will have to await the
availability and flight testing of the new booster with thrust in
the millions of pounds category in the 1965 time period.
The Soviets do not differentiate between military and non-military
space systems. They have talked of a peaceful intent of their space
program but there are many pounds of payload in their satellites
which cannot be accounted for on the basis of data given out. It
should be presumed that this could be military payloads. With this
in mind, it can be stated that during the early 1970's it is
possible that space weapon systems will be developed as a supplement
to earth-based delivery systems. It is also possible that military
facilities may have been established on or in orbit around the moon.
Atmospheric and climatic conditions will demand an air conditioned
environment for moon-based delivery systems. For increased survival
security and decreased requirements for "imported" construction
material, it seems reasonable to assume that these would be
constructed under rather than above the moon's surface.
Appendix #1 -
Glossary
Cargo Package
The Lunar Cargo Package (See Figure A-1, item e) is that part of the
Cargo Payload which represents a package consisting of supplies,
equipment, etc., needed on the lunar surface. Preliminary design
data implicates that an amount in excess of 40,000 pounds must and
can be delivered to the lunar surface.
Cargo Payload
The Cargo Payload is that part of the Lunar Transport Vehicle which
in placed on a selected lunar trajectory and is boosted to earth
escape velocity. It consists of two major parts. These are:
Lunar Landing Stage
Cargo Package
This division is schematically represented in Figure A-1 by the
parts labelled b and e. The cargo payload does not include a
Lunar Launch Stage since the cargo package remains on the lunar
surface. The weight of the Cargo Package is equivalent to the
combined weight of the Lunex Re-entry Vehicle (3 men) and the
Lunar Launch Stage. The Cargo Payload weighs 134,000 pounds at
earth escape.
Circumlunar
A highly elliptical trajectory that goes around the moon and
returns to the earth.
Circumlunar Propulsion stage
A stage attached to the Lunex Re-entry Vehicle to provide a
suitable propulsion and control capability for maintaining the
Re-entry Vehicle on a circumlunar trajectory.
Delayed Procurement Concept
Concept of deferring the final ordering and production of
high-cost insurance type spares until maximum flight experience
is available.
Hi-Speed Re-entry Test
A test program using a special Re-entry Test Vehicle
designed to obtain fundamental re-entry data and specific
configuration data am re-entry velocities of 25 to 45 thousand
feet per second.
Lunar Expedition Facility
A facility designed to be constructed under the lunar
surface and to support the Lunar Expedition. This facility will
be designed so that it can be readily expanded to support future
military requirements.
Lunar Landing Stage
The Lunar Landing Stage is that part of the Manned Lunar
Payload that will land the Manned Lunar Payload at a selected
site on the surface of the moon. The expended portion of this
stage is left on the lunar surface when the Lunex Re-entry
Vehicle is launched for the return trip to earth (See Figure
A-1, item b.).
Lunar Landing Stage - Cargo
The Lunar Landing Stage of the Cargo Payload (See Figure
A-1, item b) is identical to the landing stage of the Manned
Lunar Payload. It provides the capability of soft landing the
Cargo Package at a preselected site. The Cargo Payload is
unmanned and the landing operation is automatic. The Lunar
Landing Stage remains on the lunar surface with the Cargo
Payload.
Lunar Launch Complex
The Lunar Launch Complex consists of the base facilities,
integration buildings, checkout buildings, launch pads,
propellant manufacturing plants, the complex control centre and
all of the equipment required to earth launch and support the
Lunar Expedition.
Lunar Launching Stage
The Lunar Launch Stage (See Figure A-1, item c) is that part
of the Manned Lunar Payload that will boost the Lunex Re-entry
Vehicle to lunar escape velocity on a moon-to-earth trajectory.
It will be ejected prior to earth re-entry.
Lunar Team
The Lunar Team consists of Air Force technical personnel
from various Air Force System Command organisations and the
various Air Force Command organisations. This team was formed to
assist the SSD in establishing a sound Lunar Expedition program.
The membership during the past two years has varied from 30 to
50 personnel.
Lunar Transport Vehicle
The Lunar Transport Vehicle is required to transport men and
materials for the Lunar Expedition. The Lunar Transport Vehicle
consists of a Space Launching Vehicle and one of two payloads.
One payload is the Manned Lunar Payload and the other is the
Cargo Payload (See Figure A-1).
Lunex
Lunex is a short title for the Lunar Expedition Program
Lunex Program Director
The Lunex Program Director is the individual responsible for
directing and controlling all facets of the Lunar Expedition
Program.
Lunex Re-entry Vehicle
The Lunex Re-entry Vehicle (See Figure A-1, item d) is the
only part of the Manned Lunar Payload that returns to the earth.
It carries three men and all the necessary life support,
guidance, and communication equipment that is required. It
re-enters the earth's atmosphere and uses aerodynamic braking to
slow down and land like a conventional airplane. The preliminary
design of the Lunex Re-entry Vehicle calls for a vehicle 52 ft.
long with a return weight of 20,000 pounds.
Man-rated
A vehicle, or system is considered to be "man-rated" when
sufficient ground and flight test data has been accumulated to
determine that the reliability objectives for the item have been
achieved and that the abort system satisfactorily compensates
for the inherent unreliability of the system.
Manned Lunar Payload
The Manned Lunar Payload is that part of the Lunar Transport
Vehicle which is placed on a selected lunar trajectory and is
boosted to an earth escape velocity of approximately 37,000 feet
per second. It consists of three major parts. These are:
This division is schematically
represented in Figure A-1 by the parts labelled b, c, and d. The
complete Manned Lunar Payload weighs 134,000 pounds at earth
escape.
Responsive Production Concept
A concept whereby long lead portions of high-cost
operational spares are purchased unassembled to reduce costs
until final decision is made on spares procurement.
Space Launching System
The complete system, including ground faculties, propellant
manufacturing facilities, etc., as required to launch the
boosters required for space operations.
STANDARD TERMINOLOGY
AGE
A term used to describe the Aerospace Ground Environment
required for a specified system.
Abort System
The Abort System includes all the equipment required to remove,
or return the crew members of the Lunex Re-entry Vehicle to a
position of safety in the event of a malfunction of the Lunar
Transport Vehicle.
PEP
P.E.P. are the initials for "Program Evaluation Procedure". It
is a management tool which uses an electronic digital computer.
It has the capacity to handle large masses of date quickly. The
PEP system provides information that will enable the Lunex
Program Director to quickly identify, locate, and consequently,
correct program trouble spots.
QQPRI
A term used to describe Qualitative and Quantitative Personnel
Requirements Information that is required to properly plan for
personnel training.
RPIE
A term meaning Real Property Installed Equipment that is
synonymous with Technical Facilities. Technical Facilities are
those structural and related items which are built and/or
installed by the Corps of Engineers and then turned over to the
Air Force or an Air Force contractor.
USAF Lunar Chart
A chart prepared to a scale of 1:1,000,000 and covering the
lunar surface. Present plans call for the preparation of 144
individual charts to cover the complete lunar surface.
PROGRAM TITLES
BOSS
BOSS is the designation for "Biomedical Orbiting Satellite
System". The BOSS program uses primates to provide life science
data for designing manned space systems.
SAINT
The SAINT program will develop and demonstrate orbital
rendezvous and satellite inspection techniques. It will further
demonstrate the capability of closing, docking, and refuelling.
Back to Contents
|